Progress Report

Column Filters

Weekly Reports

Name of WorkBoring & intallation of Tubewell (Morinda)
Agency NameM/s J.P. Sons, Jalandhar
Project CostRs 33 Lacs
Start Date 30-08-2016
End Date31-12-2017
Revised Date31-12-2018
Je InchargeSh. Pardeep Kumar
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 2
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM 100 % % % % %
Financial Progress :21.98 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-11-28 12:23:38
Comment by JE in last visit : transform installed, installation of meter yet to be pending, concerned je on leave.
Observation Raised by JE :All is well
Date of Visit by SDO :2018-11-26 14:18:13
Comment by SDO :Today contacted Sh Ranjit Singh JE PSPCL he assured that connection will be released within two days
Observation Raised by SDO :
Date of Visit by XEN :2018-10-29 13:22:15
Comment by XEN on last visit :Connection with existing water supply line done, electric connection awaited, transformer procured by PSPCL.
Observation Raised by XEN :
Date of Visit by SE :2018-04-25 09:26:45
Comment by SE on last visit :1no tube well commissioned. Machinary yet to be lowered for 2nd tube well. Work delayed.Penalty imposed. EE to ensure early completion in view of summer season.
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :Proceed according to CA. The work should not be left on the mercy of the contract
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :Yes (1)-2018-04-27 00:07:51
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No