Scope of Work Component Wise |
|
|
|
2 |
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
100 % |
% |
|
|
|
% |
% |
% |
Financial Progress : | 21.98 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-11-28 12:23:38 |
Comment by JE in last visit : | transform installed, installation of meter yet to be pending, concerned je on leave. |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-11-26 14:18:13 |
Comment by SDO : | Today contacted Sh Ranjit Singh JE PSPCL he assured that connection will be released within two days |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-10-29 13:22:15 |
Comment by XEN on last visit : | Connection with existing water supply line done, electric connection awaited, transformer procured by PSPCL. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-04-25 09:26:45 |
Comment by SE on last visit : | 1no tube well commissioned. Machinary yet to be lowered for 2nd tube well. Work delayed.Penalty imposed. EE to ensure early completion in view of summer season. |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Proceed according to CA. The work should not be left on the mercy of the contract |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | Yes (1)-2018-04-27 00:07:51 |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |