Inspection Report

Column Filters

Check list for inspection of Material

Dated : 2018-04-27 00:07:51

Name of WorkBoring & intallation of Tubewell
Agency NameM/s J.P. Sons, Jalandhar
Start Date30-08-2016
Completion Date31-12-2017
CostRs 33 Lac
JE InchargeSh. Pardeep Kumar
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Sr.No Description of Material As per approved scope of agreement Already Inspected Already received at site In Transit Balance as per approved scope of agreement Now offered for Inspection Make Balance Remarks
1 Dosing Pumps 2 0 0 0 2 2 Asia LMI 0
2 Submersible Pump Set 2 1 1 0 1 1 SU 0
3 Submersible Cable 250 m 125 m 125 m 0 125 m 150 m Finolex 0
4 Control Panel 2 1 1 0 1 1 L&T 0
5 DI pipe 380 m 0 0 0 380 m 380 m As per IS : 8329 0
6 MS column Pipe 100 m 51 m 51 m 0 51 m 51 m As per IS:1978-1982 0
7 DI Specials 1 Job 250 Kg 250 Kg 0 250 Kg 250 Kg As per IS:9523-2000 0
8 CI Specials 0 0 0 0 1 Job 1 Job ISI marked 0