1 |
2021-09-30 00:00:00 Comment: Work not started 0%
|
2021-09-20 00:00:00 Comment: At the time of visit, work of laying I/L tiles was in progress at site.
Near H/N289 and near H/o Sangita Kesari, thickness of lean concrete +bedding sand + i/L tiles was checked and found as per esti 50
|
2021-10-30 00:00:00 Comment: Near H/N289 and near H/o Sangita Kesari, the thickness of lean concrete + bedding sand + I/L
tiles found as per estimate i.e (100+60+40) mm. Concerned JE/SDE Corporation should
recheck the thi 80%
|
Comment: |