Inspection Details

Column Filters

Work Details

Name of WorkP/F 60mm ISI marked I/L tiles near mohalla sangran pulli towards alongmain drain nala near attai shah dera in w.no 4
Town NameAdampur
District NameJALANDHAR
Approved Amount 6.1
Awarded Amount4.09
Award Letter Ref12/39 05/10/2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-02-13 00:00:00
Comment: During the time of visit, excavation for construction of Road gullies and dismantling of road was in progress. In street of Joginder singh the work of dressing of earth surface was in progress.
30%
2021-10-01 00:00:00
Comment: Quantity of cement was less in the lean concrete. R/G chamberDimensions was checked and found under size. Thickness of lean concrete was checked and found as per estimate
75%


Comment: