Inspection Details

Column Filters

Work Details

Name of WorkDB Paving in ward no.9 street mugar master wali, street no.1 near labu Gurudwara,karm mistri wali, makhan dandiwal wali and new Const.of Nala near labu Gurudwara
Town NameGiderbaha
District NameMUKTSAR
Approved Amount 24.09
Awarded Amount22.89
Award Letter Ref2054 DT.7-9-2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-09-30 00:00:00
Comment: The earth work spread over the DB found in excess amount. Needs to be broomed. For earth filling having depth more than 1’ proper L-sections & X-sections showing the existing NGLs & final proposed
30%
2021-10-25 00:00:00
Comment: “SK” make Bricks were being used at site.  Joints of brick work were not properly filled as per specification.  No test report of material i.e. fine and coarse aggregate, Bricks and I/L ti
85%


Comment: