2020-12-14 00:00:00 Comment: Proposed site for construction of road. 0%
|
2021-01-21 00:00:00 Comment: uPVC pipes ISI Marked Class-3 of Aravali make were stacked at site.
At the starting point of street near Bus stand, some pipes were laid in trenches without sand cushion. Proper sand cushion shou 30
|
2021-02-08 00:00:00 Comment: The thickness of bedding sand and lean concrete under I/L tiles was randomly checked at the beginning of the road, near computer shop and found as 30 mm and 35 mm. The average thickness of bedding san 70%
|