1 |
2020-12-18 00:00:00 Comment: Proposed site for Upgradation of market. 0%
|
2021-02-10 00:00:00 Comment: The rubble masonry was laid at site and a wall is constructed upto height of 4 feet at site
Inspection note for the material used at site should be provided to the 3rd party audit team during nex 30%
|
2021-10-01 00:00:00 Comment: At the time of visit no work was in progress at site of work.
In three pockets of Green Belt Phase-6, plants of different varieties were planted.
The Engineer in charge must ensure that plants/s 75%
|
Comment: |