2020-12-10 00:00:00 Comment: At the time of visit the work of excavation of earth work was in progress
● At the proposed sites of work existing streets were Katcha.
● For proper drainage the longitudinal and camber should b 10%
|
2020-11-23 00:00:00 Comment: Suitable caution boards etc. were not placed at site of work.
The CC 1:8:16 laid at site with hand mix instead of mechanical mix.
Near electricity pole No. 07/09 the thickness of bedding sand under 35%
|
2021-09-30 00:00:00 Comment: The thickness of bedding sand and base concrete under I/L 60mm tiles were randomly
checked near House of Sukhdev Singh and House of Balwinder Singh, the thickness of
bedding sand observed as 30mm & 70%
|