2021-01-18 00:00:00 Comment: No lab was shown by concerned JE, setup by the contract agency.
As per clause 6.1 of notification no. 5/8222/2018-2LG4/1892 dated 02.08.2018 standard
operating procedure issued by the departmen 10%
|
Comment:
|
2021-10-06 00:00:00 Comment: • NO approval for site change and change in nature from the competent authority to the third party.
• As per the work order the time required to complete the work is for 09 months which is elapse 70%
|
2022-11-03 00:00:00
Comment: • Length of streets 5 &3 (ward no. 68) and New ROOP NAGAR (ward no. 69) were checked and found as per entered in MB and completion plan.
• At the above-mentioned places, interlock tiles were foun100% |