1 |
2021-01-18 00:00:00 Comment: Location of site are shown by concerned JE for any change of site and change in scope of
work approval from DUIC should be taken before start of work and same to be submitted
to TPI audit team 10%
|
Comment:
|
2021-10-06 00:00:00 Comment: • NO approval for site change and change in nature from the competent authority to the third party.
• As per the work order the time required to complete the work is for 09 months which is elapse 70%
|
2022-11-03 00:00:00
Comment: • Length of different streets (WARD NO.58) & streets IN BANGLA Basti were checked and found as per entries in the MB and completion plan.• At the above-mentioned places, interlock tiles were found100% |