Inspection Details

Column Filters

Work Details

Name of WorkProviding & Laying Interlock Tiles on Berms from Fokal Point to Water Works, Ward No. 2
Town NameJoga
District NameMANSA
Approved Amount 16.73
Awarded Amount10.67
Award Letter Ref18/03 dt. 04.12.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-12 00:00:00
Comment: Proposed site for P/L of I/L tiles.
0%
2021-10-01 00:00:00
Comment: ● Near H/o Parjapat Bhoriya Singh and two places near bore of Roop Singh bedding sand and lean concrete found as an average value 35mm and 95mm instead of 50 mm & 100 mm respectively. ● Departme
45%
2021-10-01 00:00:00
Comment: • At the time of visit works in progress. • At random the thickness of bedding sand and base concrete checked at 2 points near Beant Kaur house and for 5 meters ahead from the previous point & f
70%


Comment: