1 |
2021-01-07 00:00:00 Comment: Proposed site for laying of P/L of CC flooring. 0%
|
2021-02-10 00:00:00 Comment: Contraction & Expansion joints were not filled with joint sealing compound.
Pug marks, tyre marks found on the surface of concrete needs to be got rectified
No test reports i.e cube test, Sl 45%
|
2021-08-02 00:00:00 Comment: 4” CC slab flooring has been done at site, which is as per provisions made in the estimate.
Dimensions of road gully chambers were checked at site and found under sized.
Payment of R/G should be d 80
|
Comment: |