1 |
2021-01-07 00:00:00 Comment: Proposed site for P/L of CC flooring. 0%
|
2021-02-10 00:00:00 Comment: Contraction & Expansion joints were not filled with joint sealing compound.
Pug marks, tyre marks found on the surface of concrete needs to be got rectified
No test reports i.e cube test, Sl 45%
|
2021-08-02 00:00:00 Comment: 4” CC slab flooring has been done at site, which is as per provisions made in the estimate.
R/G size found under specification at site.
Payment of R/G should be done as per actual work done at si 80
|
Comment: |