1 |
2020-12-22 00:00:00 Comment: At the time of visit the work of leveling of Katcha road was in progress 5%
|
2021-01-15 00:00:00 Comment: Near open plot the thickness of lean concrete 1:8:16 found in order. Laying of lean concrete was done manually. AME/JE should check the thickness at some more points & the payment of actual work execu 30%
|
2021-09-30 00:00:00 Comment: Thickness of slab measured at Rajbir Wali Gali was found to be 3.0 inches. Concerned JE
should ensure that work should be done as specifications. Concerned JE should recheck the
thickness at site b 70%
|
Comment: |