2020-12-22 00:00:00 Comment: At the time of visit, work of laying RMC M-20 was not started at site 0%
|
2021-01-15 00:00:00 Comment: At the time of visit the work of dismantling of existing CC near Chintpurni mandir and other area were completed & construction of R/G chamber was in progress at the time of visit.
Display board 30%
|
2021-09-30 00:00:00 Comment: Thickness of slab measured near Mata Chintpurni Mandir was found to be 3.0 inches.
Concerned JE should ensure that work should be done as specifications. Concerned JE should
recheck the thickness a 70%
|