Inspection Details

Column Filters

Work Details

Name of WorkStreets in sansian basti
Town NamePatti
District NameMohali
Approved Amount 2.62
Awarded Amount2.53
Award Letter RefWork order no 74/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-02 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:

2021-10-02 00:00:00
Comment: • Non-ISI marked Manhole covers were being used at site. Immediate rectification of the same should be ensured or necessary recovery should be made from the contractor. • ISI Marked ‘ACT’ mak
80%


Comment: