Inspection Details

Column Filters

Work Details

Name of WorkP/L Sewerline and CCF in street from h/o Baldev Singh to Govt. Girls School W.No.8
Town NamePatti
District NameMohali
Approved Amount 4.11
Awarded Amount4
Award Letter RefWork order no 65/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-02 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:

2021-11-24 00:00:00
Comment: Thickness of CC was checked near and along the School and found as per norms. Road gully couldn’t be checked due to its fixation with CC, MC officials must ensure Construction of R/G chamber stri
80%


Comment: