Inspection Details

Column Filters

Work Details

Name of WorkConstruction of R/ Gulies and CCF in Bazar from Rahul Karyana store to Santokh Kawaria Harijan Colony to Main Bazar Railways Road W.No.8
Town NamePatti
District NameMohali
Approved Amount 5.91
Awarded Amount5.76
Award Letter RefWork order no 49/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-02 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:

2021-11-24 00:00:00
Comment: The thickness of bedding sand and lean concrete laid under ISI marked 60mm interlocking tiles was randomly checked near Guru Nanak Telecom and found - thickness of (I/L Tile + bedding sand) 100mm,
80%


Comment: