Name of WorkP/L W/S Line from Gurudwara Nanakpuri to h/o Dalbir Singh Sekhon W.No.8
Town NamePatti
District NameMohali
Approved Amount 3.12
Awarded Amount3.03
Award Letter RefWork order no 46/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-02 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:


Comment:



Comment: