Inspection Details

Column Filters

Work Details

Name of WorkConstruction of CCF in street from H/o Balraj Badhwar to Tarsel Lal W.No.4
Town NamePatti
District NameMohali
Approved Amount 5.13
Awarded Amount4.95
Award Letter RefWork order no 45/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-02 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:

2021-11-24 00:00:00
Comment: Thickness of CC flooring was checked near and alongside New look saloon, house of Jagtar Singh and found as per the norms of the estimate. Road gully couldn’t be checked due to its fixation with
80%


Comment: