Inspection Details

Column Filters

Work Details

Name of WorkConstruction of CCF in street Lyallpuri from H/o Swaran Singh to H/o Kartar Singh W.No.4
Town NamePatti
District NameMohali
Approved Amount 5.28
Awarded Amount5.09
Award Letter RefWork order no 44/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-02 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department w
0%

Comment:

2021-11-24 00:00:00
Comment: Thickness of CC was checked near and along the Tikka General Store, house no. B-II 573 and found as per the norms of the estimate. Road gully couldn’t be checked due to its fixation with CC, MC o
80%


Comment: