Inspection Details

Column Filters

Work Details

Name of WorkConstruction of CCF in Gali No. 6 from H/o Harbhajan Singh to Bawa Singh W.No.4
Town NamePatti
District NameMohali
Approved Amount 3.68
Awarded Amount3.53
Award Letter RefWork order no 43/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-01 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:

2021-11-24 00:00:00
Comment: Road gully couldn’t be checked due to its fixation with CC, MC officials must ensure Construction of R/G chamber strictly as per CSR with proper dimensions e.g. finished inner sides as 2’x1-6”
80%


Comment: