Inspection Details

Column Filters

Work Details

Name of WorkS/L Sewer line and Construction of CCF from H/o Jathedar Niranjan Singh MLA to Jain Karyana Store
Town NamePatti
District NameMohali
Approved Amount 23.78
Awarded Amount23.23
Award Letter RefWork order no 41/7 dated 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-01 00:00:00
Comment: 1) At a time of visit the work is not started. 2) The time limit to complete the work has already been elapsed on date 26.01.2021. But no copy of time extension granted to agency by the department
0%

Comment:

2021-11-24 00:00:00
Comment: Thickness of CC was checked near House of Nirmal Singh & Surjeet Singh, and found as per the norms of the estimates. Road gully chambers could not be checked as they were tightly fixed with CC, MC
80%


Comment: