Inspection Details

Column Filters

Work Details

Name of WorkConst. of Drains in different area of Bariwala
Town NameBariwala
District NameMUKTSAR
Approved Amount 20.25
Awarded Amount18.27
Award Letter Ref556
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-25 00:00:00
Comment: Proposed site for construction of drains.
0%
2021-07-29 00:00:00
Comment: ime period to complete the work has already been completed on 28.01.2021 but the work is in progress at site. Documents regarding extension of time limit given to the contractor were not provided
45%

Comment:



Comment: