Name of WorkP/L Interlocking Tiles In Aman Master, Suresh Kumar Asi W No.13 Moonak
Town NameMoonak
District NameSANGRUR
Approved Amount 4.77
Awarded Amount3.56
Award Letter Ref17/10 Date 27.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-11 00:00:00
Comment: Proposed site for P/L of I/L tiles.
5%

Comment:

2021-10-01 00:00:00
Comment:  For Earth filling having depth more than 1’ proper L-section & X-section showing the existing natural ground level (NGL) & final proposed level of earth filling be prepared & provided to the W
80%