1 |
2021-10-04 00:00:00 Comment: • Product Specifications submitted but test certificates and inspection notes not submitted. Inspection report and test certificates duly signed by contractor and PWD officials shall be submitted.
10%
|
2021-10-04 00:00:00 Comment: Only 19 poles out of 20 GI octagonal poles are installed at site.
Shuttering of octagonal poles not of proper size.
Payment should only be made after the LED light certificates are received 45%
|
2021-11-24 00:00:00 Comment: No built drawing is shown to inspection team. Built drawing should be submitted for scrutiny and records. As per SBD if as built drawing is not submitted than a deduction of 1% or Rs.10000.00 should b 80
|
Comment: |