2021-10-01 00:00:00 Comment: 1) At the time of visit the work was not started.
2) No copy of agreement signed between agency & the department was provided to TPA team.
3) The Copy of allotment letter is not signed by the conc 0%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit, the casting of RCC columns was in progress at site.
2) The detailed structural drawing shown/provided to TPA team were not gotten approved from the Engineer in Charge.
3) A 35%
|
2021-11-24 00:00:00 Comment: At the time of visit, the painting work and the work of fixing doors and windows was in progress at site.
At random, the thickness of lean concrete was checked at 3 places and found in order i.e 100m 70
|