2021-10-01 00:00:00 Comment: 1)At the time of visit the work for laying lean concrete was in progress.
2) The thickness of lean concrete randomly checked at 4 places and the average of lean concrete observed as 83mm instead of 5%
|
2021-10-04 00:00:00 Comment: 1)At the time of visit, the work for white wash, distemper & painting of stadium was inprogress at site and the work of tile flooring was completed near the entrance of thestadium.
2)The thickness o 45%
|
2022-05-31 00:00:00 Comment: During the inspection of stadium work it was found that most of the sanitary fittings were
missing. During the previous visit the sanitary items were found installed and fitted at site.
It seems tha 80%
|