2021-10-01 00:00:00 Comment: 1) At the time of visit the work of dismantling of old structure was in progress.
2) Proper recovery of dismantled material may be made from the contractor bill.
3) Proper record should be maintaine 5%
|
2021-10-04 00:00:00 Comment: 1) At the time of visit, the work of excavation & levelling of ground level was in progress at site.
2) No plan showing the plinth level, ground level & formation level of the parking area was made 45%
|
2022-03-21 00:00:00 Comment: At random the thickness of bedding sand and lean concrete checked and found in order i.eSand=40mm and GSB=150mm as per estimate.
No test reports of material being used at site shown to TPA team.
Co 80%
|