Inspection Details

Column Filters

Work Details

Name of WorkP/Laying Bitumen Concrete on damaged road from Babhaur sahib to Railway crossing Nangal Dam, Ward No. 16.
Town NameNangal
District NameROPAR
Approved Amount 60.33
Awarded Amount58.52
Award Letter Ref3704/39 dt. 30.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-06 00:00:00
Comment: Proposed site for P/Laying of bitumen concrete.
10%

Comment:

2020-12-31 00:00:00
Comment: • At the time of visit, the work of marking the C/L and fixing of cat eye was in progress on site. • The compaction of SDBC on the edges was not proper. • Honey combing and segregation on the
75%
2021-09-30 00:00:00

Comment: • Thickness of SDBC was checked at site randomly and found to be in order. • The length of road marked as 8784’ on completion plan was checked at site and found as per completion plan provided100%