1 |
2021-09-30 00:00:00 Comment: Work was not started at the time of visit. 0%
|
Comment:
|
2020-12-31 00:00:00 Comment: • At the time of visit, the work of marking the C/L and fixing of cat eye was in progress on site.
• The compaction of SDBC on the edges was not proper.
• The crossings and speed-breakers on t 75%
|
2021-09-30 00:00:00
Comment: Thickness of SDBC was randomly checked at site and found as per specifications in the sanctioned estimate.
• The length of road marked as 1016’ on completion plan was checked at site and found as100% |