Name of WorkS/E Mini High Mast Light Near Ajuba Gate
Town NameAnandpur Sahib
District NameROPAR
Approved Amount 1.64
Awarded Amount1.35
Award Letter Ref37/15 09.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-14 00:00:00
Comment: • The material delivered at site was not as per specifications. Octagonal poles were laid at site instead of tubular poles. • Copy of approval of change in specification was not provided by the
0%

Comment:

2021-12-21 00:00:00
Comment: Mast Light poles of make ‘Utkarsh’ were fixed at site with length of 16m and 6 ‘Crompton’ LED lights of 180 Watt were used at site near parking of MC office. No test report of luminaries an
70%