Inspection Details

Column Filters

Work Details

Name of WorkConst.of Street & drain from H/O Keshwa Nand to Bholi in Ward No.1 M.C. Sri Anandpur Sahib
Town NameAnandpur Sahib
District NameROPAR
Approved Amount 7.2
Awarded Amount6.95
Award Letter Ref37/5 09.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-14 00:00:00
Comment: • For earth filling having depth more than 1’ proper L-sections & X-sections showing the existing NGLs & final proposed formation levels of earth filling should be prepared & provide to the WAPCOS
0%
2021-12-21 00:00:00
Comment: The width of boulder masonry retaining wall was checked at two places and found 450mm and 600mm. The width of the wall is varying along the length. So, payment for actual work executed at site shoul
50%

Comment:



Comment: