1 |
2021-10-01 00:00:00 Comment: • At the time of visit work was in progress at site.
• For old I/L Tiles present at the Berm proportionate recovery should be done from the contractor.
5%
|
2021-10-01 00:00:00 Comment: Thickness of concrete was checked and found 55mm and 70mm instead of 70mm
Height of boundary wall checked and found 31 inches instead of 36inchs
Time limit for completion of work has expired 45%
|
2022-05-17 00:00:00 Comment: • As informed by the concerned JE, work for beautification of boundary wall was finished. Whereas, in front of Park Entry Gate, grills of boundary wall were found not properly painted. It needs to b 85%
|
Comment: |