Name of WorkRaising level of stadium & repair of building in sujanpur
Town NameSujanpur
District NamePATHANKOT
Approved Amount 23.06
Awarded Amount22.14
Award Letter Ref31/42 dt 19.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-01 00:00:00
Comment: • Work of level formation at stadium was in progress with the help of JCB.
5%
2021-10-01 00:00:00
Comment: Stadium step was not repair properly No record done for earth filling Time limit elapsed
30%
2022-05-17 00:00:00
Comment: • During visit, it was informed by the concerned JE, that the work of aluminium & glass fitting is completed for doors and windows • Wall tile work at toilet block of Bleachers was finished on th
80%


Comment: