2021-10-01 00:00:00 Comment: • At the time of visit repairing work was in progress.
• Many portions of building found time worn because of moisture, comes from water tank placed on top. 10%
|
2021-10-01 00:00:00 Comment: Wall paint of one room was in shabby
Time limit for completion of work has expired
Toilet, glass work, tile work was in progress 45%
|
2022-05-17 00:00:00 Comment: • During visit, it was informed by the concerned JE, that the work of aluminium & glass fitting is completed.
• It was observed that on the top portion of the building the distemper was not prope 80%
|