Work Details

Name of WorkRepair of community hall & construction of servent room,sujanpur
Town NameSujanpur
District NamePATHANKOT
Approved Amount 24.51
Awarded Amount23.47
Award Letter Ref29/42 dt 19.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-01 00:00:00
Comment: • At the time of visit repairing work was in progress. • Many portions of building found time worn because of moisture, comes from water tank placed on top.
10%
2021-10-01 00:00:00
Comment: Wall paint of one room was in shabby Time limit for completion of work has expired Toilet, glass work, tile work was in progress
45%
2022-05-17 00:00:00
Comment: • During visit, it was informed by the concerned JE, that the work of aluminium & glass fitting is completed. • It was observed that on the top portion of the building the distemper was not prope
80%