1 |
2020-12-15 00:00:00 Comment: Proposed site for P/L of I/L tiles. 0%
|
Comment:
|
2021-02-06 00:00:00 Comment: • Front of H/o Janta singh, Amrik and H/o Sita Ram S/o Prem thickness of bedding sand and lean concrete under I/L tiles randomly checked and observed as (I/L tiles + sand) 85mm, 90mm and 88mm resp 85%
|
2023-01-05 00:00:00
Comment: •Length of the Nand street was checked at site and found as per the completion plan provided by the department.
•The thickness of lean concrete found less as per previous visit reports, but the d100% |