1 |
2020-12-15 00:00:00 Comment: Proposed site for P/L of I/L tiles. 0%
|
2021-02-06 00:00:00 Comment: • The thickness of bedding sand and lean concrete under I/L tiles randomly checked in-front of H/o Mohinder Singh Fatewala, Karishan lal Karyana store and Laxmzn Doodh wala and found in order. 45%
|
Comment:
|
2023-01-05 00:00:00
Comment: •Length of the Gurlal shni wali street was checked at site and found as per the completion plan provided by the department.
•As per T&C the time limit to complete the work exhausted on 19.11.2020100% |