Inspection Details

Column Filters

Work Details

Name of WorkGroup 9
Town NameBareta
District NameMANSA
Approved Amount 10.11
Awarded Amount6.94
Award Letter Ref046/04 dt. 12.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-08 00:00:00
Comment: Near the electricity meter box the thickness of bedding sand was checked and found 30mm against 40mm and base concrete was found 80mm against 100mm. i.e. the bedding sand observed 10mm less and base c
10%
2021-02-04 00:00:00
Comment: Near the T-20 & H-68 the thickness of bedding sand & lean concrete was checked and found 165mm against 200mm i.e. observed 35mm less than the required.
45%
2021-09-30 00:00:00
Comment: P/L interlocking Tile at Prem Subzi Wala Street, Ward No. 1  Near Mid Portion of the street, thickness of bedding sand and lean concrete under I/L 60mm tiles was checked and found the bedding sa
70%


Comment: