1 |
2020-12-08 00:00:00 Comment: Proposed site for P/L of I/L tiles. 5%
|
2021-02-04 00:00:00 Comment: At random, near P-46, thickness of bedding sand under I/L tiles checked and found 30mm against 40mm which is 10mm less than required.
● Department must ensure the work is being executed as per spec 45%
|
2021-09-30 00:00:00 Comment: P/L interlocking Tile at Harbans Vakeel Street, Ward No. 7
Near mid portion of Street the thickness of bedding sand and base lean
concrete under I/L 60mm tiles were checked and found bedding sa 70%
|
Comment: |