Work Details

Name of WorkGroup 3
Town NameBareta
District NameMANSA
Approved Amount 14.17
Awarded Amount14.01
Award Letter Ref001/05 dt. 04.11.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-08 00:00:00
Comment: Proposed site for laying of PC on road.
10%
2021-02-04 00:00:00
Comment: At the time of visit the work of laying of PC was in progress.  Near Naseeb Chand Ashok Kumar shop, thickness of the PC was checked and found in order.
45%
2021-09-30 00:00:00
Comment: As per T&C the time limit to complete the work elapsed on 03.03.2021, no document regarding extension of time limit to complete the work , wasprovided by MC officials. No job mix formula of Bitumin
70%


Comment: