1 |
2020-12-14 00:00:00 Comment: Work not started yet. Nil
|
2021-10-01 00:00:00 Comment: • Near the H/o Bhalla Singh and Manjeet Singh thickness of bedding sand under 60mm I/L tiles was checked and found 30mm against 40mm and average thickness of base concrete was found to be 55mm again 45%
|
2021-10-01 00:00:00 Comment: Near End Portion of House no.727 workmanship regarding laying of I/L tiles was very
poor due to lack of timely supervision by the MC official. Engineer in-charge should
visit the site and ensure the 70%
|
Comment: |