Name of WorkP.F Interlocking tile 80 mm on Cheema Main Road Berm
Town NameKot Isse Khan
District NameMOGA
Approved Amount 43.16
Awarded Amount38.36
Award Letter Ref29/07 dt. 01.12.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-20 00:00:00
Comment: Proposed site for P/F of I/L tiles.
0%
2021-02-25 00:00:00
Comment: The thickness of bedding sand + lean concrete + I/L tiles were checked at 3 different points and found as average 150 mm instead of 200 mm which is 50 mm less than required.  Department must en
30%
2022-12-07 00:00:00
Comment: At the time of visit work was in progress. The thickness of bedding sand and base concrete under I/L 80mm tiles was checked at 2 points near Shinda Sofa Repair Shop, the thickness of bedding sand f
70%