Inspection Details

Column Filters

Work Details

Name of WorkWidening and Construction of Road from Anadiana Gate to Ram Bag
Town NameFaridkot
District NameFARIDKOT
Approved Amount 26.39
Awarded Amount22.22
Award Letter Ref055/04 dt. 31.08.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-24 00:00:00
Comment: Proposed site for widening and Construction of roads.
0%
2021-01-09 00:00:00
Comment: Construction of divider work was in progress, the grill laid on the divider was not painted yet.  Height of grill was checked and found as 2’3’’ as per specifications.  The plastering on
40%
2021-05-28 00:00:00
Comment: 1) Payment has to be made as per actual weight (weight before installation) for providing and fixing of Iron Grill and iron grill section installed. The work of installation has been completed but the
85%


Comment: