2020-12-24 00:00:00 Comment: Proposed site for laying of LED lights. 0%
|
2021-01-09 00:00:00 Comment: The cable in DWC pipe should be laid at depth of 1 metre.
Proper specifications of poles and pedestal box used was not provided by the department.
Depth of foundation of poles was checked an 30%
|
2021-10-01 00:00:00 Comment: Foundation of electrical panel box was not filled with required CC as the poles are inserted directly
in earth without filling.
It was observed during the visit that electrical Panel box install 70%
|