Inspection Details

Column Filters

Work Details

Name of WorkConst of Drain Type-1 and laying cc flooring gali opp milk plant wno 3
Town NameGurdaspur
District NameGURDASPUR
Approved Amount 19.27
Awarded Amount17.33
Award Letter Ref41/20 dated 07.08.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-10-22 00:00:00
Comment: Proposed site for laying of CC flooring and construction of drain Type-1.
10%

Comment:

2021-01-19 00:00:00
Comment:  Interlocking tiles found depressed at different places of street, it should be rectified before making any payment of the contract agency.  Brooming on the surface of tiles is yet to be done
80%
2022-12-24 00:00:00

Comment: •Length of both branch streets checked and found as per paid in MB. •The thickness of bedding sand and lean concrete laid under interlocking tiles (60mm ISI marked) was randomly checked near the 100%