1 |
Comment:
|
2021-10-02 00:00:00 Comment: • Foundation for light pole has been constructed.
• Inspection note for electrical material used at site should be prepared and submitted to TPI team during next visit.
• Length and width of f 30%
|
2021-12-15 00:00:00 Comment: • Near Govt Sen Sec School (Boys) Gurdaspur, in front of Post Office & some other random locations, the locking material of I/L Tile was found worn out. It needs to be rectified.
• Near old Tehsi 85%
|
2022-12-24 00:00:00
Comment: •As per vetted estimate, work has been sanctioned at Jahaj chowk to Parsuram chowk. But as informed by concerned JE work of laying I/L tile has been done at Jahaj Chowk to Parsuram chowk and also at100% |