Inspection Details

Column Filters

Work Details

Name of WorkP & L Interlocking Pavors ck on Road berms from Mahla Chowk to Sem Nalla Puli, Ward No. 2
Town NameMudki
District NameFEROZEPUR
Approved Amount 16.17
Awarded Amount13.72
Award Letter Ref12/45 dt. 29.12.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-13 00:00:00
Comment: Proposed site for P/L of I/L tiles.
0%w
2021-02-10 00:00:00
Comment: • At the time of visit the work was in progress. • The sand filling in joints of I/L tiles laid was found improper. • At random, thickness of bedding sand checked under 80 MM I/L tiles near
40%
2021-05-21 00:00:00
Comment: 1) The thickness of bedding sand was checked Near Bittu Cold Drink Shop and Transformer and was found in order, base concrete under 80mm I/L tiles was randomly checked, the thickness of bedding sand
80%


Comment: