2021-01-13 00:00:00 Comment: Proposed site for P/L of I/L tiles. 0%
|
2021-02-10 00:00:00 Comment: • At the time of visit the work was in progress.
• The proper record of compaction should be maintained & shown to WAPCOS team during the next visit.
• The sand filling in joints of I/L tiles 30%
|
2021-05-21 00:00:00 Comment: 1) The thickness of bedding sand and base concrete was checked at 2 points near
Bus Stand and found to be in order i.e 40mm (Sand)+100mm (Base concrete) as
per specification.
2) ISI marked ‘BTâ 80%
|