Inspection Details

Column Filters

Work Details

Name of WorkP & L Interlocking Pavors on Road berms (Left Side) from Malha Chowk to Cremation Ground
Town NameMudki
District NameFEROZEPUR
Approved Amount 26.18
Awarded Amount23.13
Award Letter Ref07/45 dt. 23.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-13 00:00:00
Comment: Proposed site for P/L of I/L tiles.
0%
2021-02-10 00:00:00
Comment: • At the time of visit the work was in progress at site. • At random, the thickness of bedding sand and lean concrete checked at two points and found 20 mm less than estimate i.e 40 mm & 100 mm.
45%
2021-05-21 00:00:00
Comment: 1) Thickness of bedding sand and base concrete was checked at 2 points near Gaushala and found in order i.e 40mm (Sand)+100mm (Base concrete) as per specification. 2) ISI marked ‘BJI’ make M4
80%